European Coordination for Accelerator Research & Development |
||||||||
|
|||||||||
The EuCARD project milestones are listed below in date order, along with links to relevant documentation when applicable.
|
Year 1 (April 2009 - March 2010) |
Year 2 (April 2010 - March 2011) |
Year 3 (April 2011 - March 2012) |
Year 4 (April 2012 - March 2013) |
|
Milestone no. |
Milestone reference |
Milestone name |
WP |
Lead |
Delivery date |
Achieved Yes/No |
Actual / Forecast achievement date dd/mm/yyyy |
Comments |
|
114 |
M11.3.1 |
Requirements for electron beam diagnostics |
11 |
STFC |
M2
|
Yes |
M2 |
Completed |
|
|
M11.3.1 |
11 |
CNRS |
N/A |
Yes |
M2 |
Additional milestone not originally foreseen in Annex 1, see report |
|
|
10 |
M3.1.1.1 |
Calendar of workshops & conferences concerning NEU2012 |
3 |
INFN |
M6 |
Yes |
M6 |
Completed, see NEu2012 website for details |
|
66 |
M9.3.3 |
Installation of ATF2 final-focus alignment monitoring system |
9 |
CNRS |
M6 |
Yes |
M16 |
Milestone objectives met by other means |
|
1 |
M1.1 |
1st annual EuCARD meeting |
1 |
CERN |
M12 |
Yes |
M13 |
Mid-April date was more suitable, more details>> |
|
6 |
M2.1.1 |
Annual status of DCO, first year |
2 |
WUT, CERN |
M12 |
Yes |
M13 |
Presented at the EuCARD 1st Annual Meeting |
|
12 |
M3.1.3.1 |
NEU2012 first annual workshop |
3 |
INFN |
M12 |
Yes |
M13 |
Scheduled during the EuCARD 1st Annual Meeting |
|
18 |
M4.1.1 |
Annual
AccNet steering meeting, |
4 |
CERN, CNRS |
M12 |
Yes |
M8 |
Two meetings organized |
|
22 |
M4.2.1 |
Annual
EuroLumi workshop, |
4 |
CERN |
M12 |
Yes |
Before M12 |
Workshop replaced by several more focused mini-workshops |
|
26 |
M4.3.1 |
Annual
RFTECH workshop, |
4 |
CNRS, TUL |
M12 |
Yes |
M12 |
Workshops held in DESY on 29/03/10 |
|
33 |
M7.1.1 |
1st annual HFM review meeting |
7 |
CERN, CEA |
M12 |
Yes |
M12 |
Held at Wroclaw Technical University (PWR)/td> |
|
38 |
M7.2.2 |
Preliminary heat deposition model for a dipole Nb3Sn
model magnet
|
7 |
PWR |
M12 |
Yes |
M12 |
Publication on web, see report |
|
42 |
M7.4.1 |
HTS conductor specifications for insert coils |
7 |
CERN |
M12 |
Yes |
M12 |
Done: first version of the specification for YBCO and Bi-2212 conductors written down. |
|
46 |
M8.1.1 |
1st annual ColMat review meeting |
8 |
CERN, GSI |
M12 |
Yes |
M12 |
Held at CERN |
|
50 |
M8.2.1 |
Functional specification LHC of beam loss and collimator design |
8 |
CERN |
M12 |
Yes |
M12 |
Simulations and design done. |
|
52 |
M8.2.3 |
Functional specification FAIR of beam loss and collimator design |
8 |
GSI |
M12 |
Yes |
M12 |
Simulations and design done. |
|
58 |
M9.1.1 |
Annual NCLinac review first year |
9 |
CERN, RHUL |
M12 |
Yes |
M13 |
Scheduled during the EuCARD 1st Annual Meeting |
|
75 |
M10.1.1 |
Annual review SRF first year |
10 |
CEA, CERN |
M12 |
Yes |
M13 |
Held at the Cockcroft Institute, UK |
|
M10.2.2 |
10 |
CEA |
M12 |
Yes |
M26 |
Milestone delayed due to change of strategy, report now available |
||
|
80 |
M10.3.1 |
LHC crab cavity specifications completed |
10 |
UNIMAN |
M12 |
Yes |
M14 |
Rescheduled following change of goals by WP4 LHC-CC09 workshop, see report |
|
83 |
M10.3.4 |
CLIC crab cavity specifications completed |
10 |
UNIMAN |
M12 |
Yes |
M15 |
Delay in recruitment of a PDRA, see report |
|
88 |
M10.4.1 |
Lead deposition on samples for photocathode development |
10 |
CERN |
M12 |
Yes |
M12 |
Samples completed. Deposition system has been rebuilt and optimised in order to achieve an efficient and free of micro-droplets coating. |
|
105 |
M10.7.1 |
Preparation system for GaAs finished |
10 |
FZD |
M12 |
Yes |
M12 |
Completed |
|
108 |
M11.1.1 |
1st annual ANAC review meeting |
11 |
INFN |
M12 |
Yes |
M13 |
Done |
|
112 |
M11.2.1 |
11 |
INFN |
M12 |
Yes |
M12 |
Preparatory for IR study completed, see report |
|
|
Milestone no. |
Milestone reference |
Milestone name |
WP |
Lead |
Delivery date |
Achieved Yes/No |
Actual / Forecast achievement date dd/mm/yyyy |
Comments |
|
115 |
M11.3.2 |
Construction of the electron beam diagnostics completed |
11 |
STFC |
M14 |
Yes |
M14 |
Completed |
|
30 |
M4.4.1 |
Get SC and GB support and agreement of coordinating institute for minimal funding |
4 |
CERN |
M18 |
Yes |
M18 |
Completed |
|
71 |
M9.4.1 |
Training at ATF3 |
9 |
RHUL |
M18 |
Yes |
M18 |
Commissioning at ATF2 done |
|
72 |
M9.4.2 |
LW and BPMs installed |
9 |
RHUL |
M18 |
Yes |
M18 |
Hardware at ATF2 and PETRAIII done. First data taking using new systems is scheduled for November 2010. |
|
89 |
M10.4.2 |
Lead deposition on half cells and 1.5 cell cavities |
10 |
CERN |
M18 |
Yes |
M19 |
Report and samples completed in M19 |
|
95 |
M10.6.1 |
10 |
DESY |
M18 |
Yes |
M19 |
Completed in M19, see report |
|
|
98 |
M10.6.4 |
10 |
DESY |
M18 |
Yes |
M19 |
Completed in M19, see report |
|
|
101 |
M10.6.7 |
Design
and manufacturing of high linearity multichannel downconverter
|
10 |
DESY |
M18 |
Yes |
M19 |
Completed in M19, see report |
|
106 |
M10.7.2 |
10 |
FZD |
M18 |
Yes |
M18 |
Installed, first measurement shifts Oct 2010, see report |
|
|
113 |
M11.2.2 |
Compatibility of new IR scheme and LHC |
11 |
INFN |
M18 |
Yes |
M18 |
Preparatory for IR study done. |
|
53 |
M8.3.1.1 |
LHC type collimator designed |
8 |
CERN |
M20 |
Yes |
M18 |
Warm collimator. Done early by Month 18 |
|
116 |
M11.3.3 |
Commissioning of EMMA completed |
11 |
STFC |
M20 |
Yes |
M25 (30/04/2011) |
Commissioning still underway. Should be complete April 2011 |
|
31 |
M4.4.2 |
Define the goals and governance structure of the network: identify 3 coordinators |
4 |
CERN |
M22 |
Yes |
M22 |
Completed. Report |
|
2 |
M1.2 |
2nd annual EuCARD meeting |
1 |
CERN |
M24 |
Yes |
M26 (13/05/2011) |
Took place 11-13 May 2011 |
|
3 |
M1.3 |
Mid-term review |
1 |
CERN |
M24 |
Yes |
M27 (21/06/2011) |
Took place 21/06/2011 |
|
7 |
M2.1.2 |
Annual status of DCO, second year |
2 |
WUT, CERN |
M24 |
Yes |
M26 (11/05/2011) |
Presentation made at annual meeting - 11th May |
|
11 |
M3.1.2.1 |
Intermediate review of NEU2012 recommendations on neutrino experiments |
3 |
INFN |
M24 |
No | n/a |
Milestone suppressed: the delay makes it collide with the deliverable it would have prepared. |
|
13 |
M3.1.3.2 |
NEU2012 second annual workshop |
3 |
INFN |
M24 |
Yes |
M26 (10/05/2011) |
Delayed to coincide with second annual meeting (10th May) |
|
16 |
M3.2.1.1 |
Intermediate review of NEU2012 recommendations on existing accelerator neutrino facilities. |
3 |
INFN |
M24 |
No | n/a |
Milestone suppressed: the delay makes it collide with the deliverable it would have prepared. |
|
17 |
M3.3.1.1 |
Intermediate review of NEU2012 recommendations on new accelerator neutrino facilities. |
3 |
INFN |
M24 |
Yes |
M37 (30/04/2012) |
Presented in the 2012 annual meeting |
|
19 |
M4.1.2 |
Annual AccNet steering meeting, second year. |
4 |
CERN, CNRS |
M24 |
Yes |
M26 (10/05/2011) |
Delayed to coincide with second annual meeting (10th May) |
|
23 |
M4.2.2 |
Annual EuroLumi workshop, second year. |
4 |
CERN |
M24 |
Yes |
M22 (31/01/2011) |
|
|
27 |
M4.3.2 |
Annual RFTECH workshop, second year. |
4 |
CNRS, TUL |
M24 |
Yes |
M21 (31/12/2010) |
|
|
34 |
M7.1.2 |
2nd annual HFM review meeting |
7 |
CERN, CEA |
M24 |
Yes |
M24 (22/03/2011) |
Link to meeting here |
|
39 |
M7.2.3 |
Engineering heat deposition model for a dipole Nb3Sn model magnet |
7 |
PWR |
M24 |
Yes |
M24 (22/03/2011) |
Presentation at HFM meeting. Report here |
|
47 |
M8.1.2 |
2nd annual ColMat review meeting |
8 |
CERN, GSI |
M24 |
Yes |
M18 (30/09/2010) |
Completed early, in September 2010 (M18) |
|
51 |
M8.2.2 |
Upgrade LHC collimator specification |
8 |
CERN |
M24 |
Yes |
M17 (31/08/2010) |
Materials characterized and tested. Review of results and specification. |
|
56 |
M8.3.2.1 |
FAIR type collimator designed |
8 |
CERN |
M24 |
Yes |
M18 (30/09/2010) |
cryogenic collimator. Done early by September 2010 (M18) |
|
59 |
M9.1.2 |
Annual NCLinac review second year |
9 |
CERN, RHUL |
M24 |
Yes |
M26 (13/05/2011) |
Delayed to coincide with annual meeting |
|
62 |
M9.2.1 |
Modification of NCLinac computer codes and first round of simulations. |
9 |
CERN |
M24 |
Yes |
M24 |
|
|
63 |
M9.2.2 |
Design of NCLinac hardware for test module |
9 |
CERN |
M24 |
Yes |
M24 |
|
|
65 |
M9.3.1 |
Characterization of noise/vibrations sources in an accelerator |
9 |
CNRS |
M24 |
Yes |
M24 |
|
|
M9.3.2 |
Installation of interferometers at CTF3 Module |
9 |
CNRS |
M24 |
No | n/a |
M24 milestone suppressed: change of strategy to reach identical deliverable. |
|
|
67 |
M9.3.4 |
Installation of ILC prototype FB/FF at ATF2 |
9 |
CNRS |
M24 |
Yes |
M24 (31/03/2011 |
|
|
76 |
M10.1.2 |
Annual review SRF second year |
10 |
DESY, CEA |
M24 |
Yes |
M26 (13/05/2011) |
Delayed to coincide with annual meeting |
|
81 |
M10.3.2 |
LHC model crab cavity completed |
10 |
ULANC |
M24 |
Yes |
M27 (30/06/2011) |
Delay after change in strategy in LHCC09. Model made in month 27, report received. |
|
84 |
M10.3.5 |
CLIC model crab cavity completed |
10 |
UNIMAN |
M24 |
Yes |
M39 (30/06/2012) |
Delayed to M38: Fabrication delays experienced. |
|
96 |
M10.6.2 |
Design
and manufacturing of the AMC modules with fast analogue and
digital IO (at least 100 Ms/s, 14 b). |
10 |
DESY |
M24 |
Yes |
M31 (03/10/2011) |
Completed in M31, see report |
|
97 |
M10.6.3 |
Design
and manufacturing of the AMC board with ultra fast ADC (at least
2 Gs/s, 10 b) |
10 |
DESY |
M24 |
Yes |
M31 (03/10/2011) |
Completed in M31, see report |
|
100 |
M10.6.6 |
10 |
DESY |
M24 |
Yes |
M31 (03/10/2011) |
Completed in M31, see report |
|
|
102 |
M10.6.8 |
Integration of downconverters and upconverters in RTM (ATCA) |
10 |
DESY |
M24 |
Yes |
M31 (03/10/2011) |
Completed in M31, see report |
|
103 |
M10.6.9 |
Design
and fabrication of AMC modules for controlling step motors,
piezo and waveguide tuners |
10 |
DESY |
M24 |
Yes |
M35 (01/02/2012) |
Completed in M35, see report |
|
107 |
M10.7.3 |
GaAs photocathodes produced |
10 |
FZD |
M24 |
Delayed |
M48 (31/03/2013) |
Manpower problems now solved. Linked to deliverable D10.7.2 |
|
109 |
M11.1.2 |
2nd annual ANAC review meeting |
11 |
INFN |
M24 |
Yes |
M26 (13/05/2011) |
Delayed to coincide with second annual meeting |
|
117 |
M11.4.1 |
Electron beam emittance meter finished |
11 |
CNRS |
M24 |
Yes |
M24 (31/03/2011) |
Complete, see report |
|
Milestone no. |
Milestone reference |
Milestone name |
WP |
Lead |
Delivery date |
Achieved Yes/No |
Actual / Forecast achievement date dd/mm/yyyy |
Comments |
|
54 |
M8.3.1.2 |
LHC type collimator constructed |
8 |
CERN |
M26 |
Yes |
M18 |
Completed early, by Month 18 (September 2010) |
|
37 |
M7.2.1 |
Methodology for the certification of radiation resistance of coil insulation material |
7 |
PWR |
M30 |
Yes |
M31 (20/10/2011) |
Minor delay due to technical and scheduling reasons, report available here |
|
43 |
M7.4.2 |
7 |
CERN |
M30 |
Yes |
M36 (07/03/2012) |
Delayed for technical reasons, 2 coils were made but problems with conductor degradation and splices needed to be solved. Report available here. |
|
|
55 |
M8.3.1.3 |
LHC type collimator tested |
8 |
CERN |
M30 |
Yes |
M36 |
Done, confirmed in Steering Committee meeting |
|
68 |
M9.3.5 |
Commissioning of CLIC quadrupole module |
9 |
CNRS |
M30 |
Yes |
M37 (30/04/2012) |
Complete module with girder and accelerating structure. All magnet prototypes now available, confirmed in Steering Committee meeting. |
|
69 |
M9.3.6 |
Quadruple mock-up manufactured and ready for installation |
9 |
CNRS |
M30 |
No |
M37 (30/04/2012) |
Several quadrupole prototypes and short model assembled. |
|
79 |
M10.2.1 |
Cavity fabrication (proton linac) |
10 |
CEA |
M30 |
No |
M42 (30/09/2012) |
Delay due to cost and tendering |
|
86 |
M10.3.7 |
Development of LHC LLRF system |
10 |
UNIMAN |
M30 |
Delayed |
M46 (31/01/2013) |
Delayed to M46: CLIC and LHC work interchanged (amendment 2) and suffering an additional delay. |
|
87 |
M10.3.8 |
Development of CLIC LLRF system |
10 |
UNIMAN |
M30 |
Yes |
M25 (30/04/2011) |
LHC and CLIC work interchanged |
|
90 |
M10.4.3 |
QWR sputtering with Nb using the magnetron technique |
10 |
INFN |
M30 |
Yes |
M36 (06/03/2012) |
Report received, awaiting approval |
|
91 |
M10.4.4 |
Report on new thin film coating techniques for SC cavities |
10 |
ULANC |
M30 |
Delayed |
M48 (30/09/2012) |
Delayed due to change of staff |
|
82 |
M10.3.3 |
LHC input and LOM mode coupler design development finished |
10 |
ULANC |
M33 |
Delayed |
M46 (31/01/2013) |
Delayed to M46. Report in preparation |
|
85 |
M10.3.6 |
CLIC input and mode coupler design development finished |
10 |
UNIMAN |
M33 |
Delayed |
M45 (31/12/2012) |
Delayed to M45. Report in preparation |
|
44 |
M7.5.1 |
Final design report HTS link |
7 |
CERN |
M34 |
Delayed |
M45 (31/03/2012) |
Delayed to M45. Report in preparation |
|
4 |
M1.4 |
3rd annual EuCARD meeting |
1 |
CERN |
M36 |
Yes |
M37 (24/04/2012) |
Took place in Warsaw (24)25-30 April, see here. |
|
8 |
M2.1.3 |
Annual status of DCO, third year |
2 |
WUT, CERN |
M36 |
Yes |
M37 (25/04/2012) |
Ppresented during Annual meeting |
|
14 |
M3.1.3.3 |
NEU2012 third annual workshop |
3 |
INFN |
M36 |
Yes |
M38 (24/05/2012) |
Was part of the Annual meeting |
|
20 |
M4.1.3 |
Annual AccNet steering meeting, third year. |
4 |
CERN, CNRS |
M36 |
Yes |
M37 (24/04/2012) |
Was part of the Annual meeting |
|
24 |
M4.2.3 |
Annual EuroLumi workshop, third year. |
4 |
CERN |
M36 |
Yes |
M27 (20/06/2011) |
|
|
28 |
M4.3.3 |
Annual RFTECH workshop, third year. |
4 |
CNRS, TUL |
M36 |
Yes |
M33 (11/12/2011) |
|
|
35 |
M7.1.3 |
3rd annual HFM review meeting |
7 |
CERN, CEA |
M36 |
Yes |
M37 (24/04/2012) |
Will be part of the Annual meeting |
|
45 |
M7.6.1 |
Short prototype SC helical undulator fabricated and tested |
7 |
STFC |
M36 |
Delayed |
M48 (31/03/2013) |
Milestone will coincide with deliverable. Deliverable will be produced without intermediate step. |
|
48 |
M8.1.3 |
3rd annual ColMat review meeting |
8 |
CERN, GSI |
M36 |
Yes |
M37 (24/04/2012) |
Will be part of the Annual meeting |
|
57 |
M8.3.2.2 |
FAIR type collimator constructed |
8 |
CERN |
M36 |
Yes |
M26 (31/05/2011) |
Completed early |
|
60 |
M9.1.3 |
Annual NCLinac review third year |
9 |
CERN, RHUL |
M36 |
Yes |
M37 (24/04/2012) |
Will be part of the Annual meeting |
|
64 |
M9.2.3 |
Prototype components for CLIC module prepared |
9 |
CERN |
M36 |
Yes |
M36 (06/03/2012) |
|
|
73 |
M9.5.1 |
RF phase monitor prototype finished |
9 |
INFN |
M37 |
Yes |
M37 (06/04/2012) |
Prototype ready for test |
|
77 |
M10.1.3 |
Annual review SRF third year |
10 |
DESY, CEA |
M36 |
Yes |
M36 (29/03/2012) |
Event 29-30 March in HZB |
|
92 |
M10.4.5 |
Improved RF-design of 1.5 cell |
10 |
DESY |
M36 |
Delayed |
M43 |
Delayed to M43. |
|
93 |
M10.4.6 |
Elliptical cavity prototype by HIPIMS |
10 |
CERN |
M36 |
Yes |
M42 (31/09/2012) |
|
|
94 |
M10.5.1 |
HOM alignment for 3.9 GHz cavity electronics verification |
10 |
DESY |
M36 |
Delayed |
M45 (31/12/2012) |
Delayed due to FLASH beam time availability |
|
99 |
M10.6.5 |
Report on tests and calibration of the radiation dosimeter |
10 |
DESY |
M36 |
Delayed |
M46 |
Report in preparation |
|
104 |
M10.6.10 |
Report on longitudinal beam parameter studies and their controllability by fast feedback systems in conjunction with the LLRF system |
10 |
DESY |
M36 |
Yes | M37 |
|
|
107 |
M10.7.3 |
GaAs photocathodes produced |
10 |
FZD |
M36 |
Delayed | M45 |
Delayed |
|
110 |
M11.1.3 |
3rd annual ANAC review meeting |
11 |
INFN |
M36 |
Yes |
M37 (24/04/2012) |
Will be part of the Annual meeting |
|
Milestone no. |
Milestone reference |
Milestone name |
WP |
Lead |
Delivery date |
Achieved Yes/No |
Actual / Forecast achievement date dd/mm/yyyy |
Comments |
|
32 |
M4.4.3 |
Annual EuroNNAc workshop 2012 |
4 |
CERN |
M39 |
Yes |
M44 (05/11/2012) |
|
|
74 |
M9.5.2 |
Electro optical monitor prototype finished |
9 |
INFN |
M40 |
No |
Prototype ready for test |
|
|
41 |
M7.3.2 |
Dipole Nb3Sn model magnet finished |
7 |
CEA |
M42 |
No |
Ready for cold test |
|
|
70 |
M9.3.7 |
Design of nm-level beam stabilization system for ATF2 |
9 |
UOXF-DL |
M42 |
No |
|
|
|
40 |
M7.3.1 |
Dipole Nb3Sn coils finished |
7 |
CEA |
M45 |
Obsolete milestone after deliverable modification |
||
|
5 |
M1.5 |
Final annual EuCARD meeting |
1 |
CERN |
M48 |
Delayed | M51 |
|
|
9 |
M2.1.4 |
Final status of DCO |
2 |
WUT, CERN |
M48 |
Delayed | M51 |
|
|
15 |
M3.1.3.4 |
NEU2012 final annual workshop |
3 |
INFN |
M48 |
Delayed | M51 |
|
|
21 |
M4.1.4 |
Final AccNet steering meeting |
4 |
CERN, CNRS |
M48 |
Delayed | M51 |
|
|
25 |
M4.2.4 |
Final EuroLumi workshop |
4 |
CERN |
M48 |
Delayed | M51 |
|
|
29 |
M4.3.4 |
Final RFTECH workshop |
4 |
CNRS, TUL |
M48 |
Delayed | M51 |
|
|
36 |
M7.1.4 |
Final HFM review meeting |
7 |
CERN, CEA |
M48 |
Delayed | M51 |
|
|
49 |
M8.1.4 |
Final ColMat review meeting |
8 |
CERN, GSI |
M48 |
Delayed | M51 |
|
|
61 |
M9.1.4 |
Final NCLinac review |
9 |
CERN, RHUL |
M48 |
Delayed | M51 |
|
|
78 |
M10.1.4 |
Final SRF review |
10 |
DESY, CEA |
M48 |
Delayed | M51 |
|
|
111 |
M11.1.4 |
Final ANAC review meeting |
11 |
INFN |
M48 |
Delayed | M51 |
|