Year 1 |
|||||||||||
|
Del. no. |
Deliverable name |
V. no. |
WP no. |
Lead Bene-ficiary |
Nat-ure |
Dissem-ination |
Delivery date from Annex I (proj month) |
Actual / Forecast delivery date | Status Not submitted / Submitted |
Contr-actual Yes / No |
Comments |
|
D2.2.1 |
EuCARD web site implementation |
1 |
2 |
WUT, CERN |
O |
PU |
M1 |
07/11/2008 | Submitted 29/05/2009 | Yes | |
|
D4.1.1 |
Continually updated AccNet web site
|
1 |
4 |
CERN, CNRS |
O |
PU |
M2 |
23/04/2009 | Submitted 08/07/2009 | Yes |
Three website deliverables: AccNet, EuroLumi and RFTECH grouped into one report. Final version delayed due to overcoming a firewall issue on CNRS web server. |
|
D4.2.1 |
Continually updated
EuroLumi web site
|
1 |
4 |
CERN |
O |
PU |
M2 |
||||
|
D4.3.1 |
Continually updated
RFTECH web site
|
1 |
4 |
UJF, TUL |
O |
PU |
M2 |
||||
|
D3.1.1 |
NEU2012
Website
operational
|
1 |
3 |
INFN |
O |
PU |
M6 |
30/09/2009 | Submitted 30/10/2009 | Yes | |
|
D10.4.1 |
1 |
10 |
DESY, SINS |
R |
PU |
M12 |
31/03/2010 |
Submitted 27/05/2010 | Yes | ||
Year 2 |
|||||||||||
|
Del. no. |
Deliverable name |
V. no. |
WP no. |
Lead Bene-ficiary |
Nature |
Dissemination level |
Delivery date from Annex I (proj month) |
Actual / Forecast delivery date | Status / Not submitted |
Contractual Yes / No |
Comments |
|
D1.1 |
1 |
CERN |
R |
PU |
M20 |
17/12/2010 | Submitted 17/12/2010 | Yes | See public version of report (with financial data removed) | ||
|
D4.3.2 |
Strategy/result for SRF test infrastructures |
4 |
CERN, TUL |
R |
PU |
M24 |
31/05/2011 |
Submitted 14/06/2011 |
Yes | Report & now a booklet | |
|
D8.1.2 |
Collimator specification for LHC upgrade parameters |
8 |
CERN, GSI |
R |
PU |
M24 |
31/08/2010 |
Submitted 14/06/2011 |
Yes | Report | |
|
D8.1.3 |
Collimator specification for FAIR |
8 |
CERN, GSI |
R |
PU |
M24 |
30/09/2010 |
Submitted 01/06/2011 |
Yes | Report | |
|
D10.7.1 |
Results of slice measurements |
10 |
FZD |
R |
PU |
M24 |
31/03/2011 |
Submitted 14/06/2011 |
Yes | Report | |
|
D10.8.1 |
Test and operation of the couplers preparation procedure |
10 |
CNRS |
R |
PU |
M24 |
31/03/2013 | Not submitted | Yes | Will be delivered M48, with intermediate milestones. Delay not critical (3 year task with no dependencies). Delay noted in contract amendment | |
|
D11.2.1 |
DAFNE IR design for the upgraded KLOE detector |
11 |
INFN |
R |
PU |
M24 |
31/03/2011 |
Submitted 30/05/2011 |
Yes | Report | |
Year 3 |
|||||||||||
|
Del. no. |
Deliverable name |
V. no. |
WP no. |
Lead Bene-ficiary |
Nature |
Dissemination level |
Delivery date from Annex I (proj month) |
Actual / Forecast delivery date | Status / Not submitted |
Contractual Yes / No |
Comments |
|
D8.3.2 |
8 |
GSI |
P |
PU |
M30 |
22/11/2011 |
Submitted 16/12/2011 |
Yes | Report | ||
|
D10.4.4 |
New thin film techniques for SC cavities and photo cathodes |
10 |
ULANC |
D |
PU |
M30 |
30/09/2012 | Not submitted | Yes | Delay noted in contract amendment | |
|
D10.2.1 |
Results of SC proton cavity tests (b = 1 and b = 0.65) |
10 |
CEA |
R |
PU |
M33 |
31/12/2012 | Not submitted | Yes | Delay due to cost/tendering | |
|
D10.7.2 |
Results for GaAs photocathodes |
10 |
FZD |
R |
PU |
M33 |
31/03/2012 | Not submitted | Yes | Milestone at M45 | |
|
D7.2.2 |
Thermal model for a dipole Nb3Sn model magnet |
7 |
PWR |
R |
PU |
M36 |
31/03/2012 | Yes | |||
|
D8.2.1 |
Report on modelling and materials |
8 |
CERN |
R |
PU |
M36 |
31/03/2012 | Yes | |||
|
D10.3.1 |
LHC crab cavity final report |
10 |
UNIMAN |
R |
PU |
M36 |
31/07/2012 | Yes | |||
|
D10.3.2 |
CLIC crab cavity final report |
10 |
UNIMAN |
R |
PU |
M36 |
31/07/2012 | Yes | |||
|
D10.3.3 |
LHC and CLIC LLRF final reports |
10 |
UNIMAN |
R |
PU |
M36 |
31/07/2012 | Yes | |||
|
D10.4.2 |
RF measurements on thin film deposited QRW prototype |
10 |
CERN |
R |
PU |
M36 |
31/03/2013 | Yes | Delay noted in contract amendment | ||
|
D10.4.3 |
Cold test results for the test cavities w/out the deposited lead photo cathode |
10 |
CERN |
R |
PU |
M36 |
Yes | ||||
|
D11.2.2 |
Study of an IR design for LHC upgrade |
11 |
INFN |
R |
PU |
M36 |
Yes | ||||
|
D11.3.1 |
Results from the operation of EMMA using the new diagnostics |
11 |
STFC |
R |
PU |
M36 |
Yes | ||||
|
D11.4.1 |
Preliminary electron beam emittance measurement report |
11 |
CNRS |
R |
PU |
M36 |
Yes | ||||
Year 4 |
|||||||||||
|
Del. no. |
Deliverable name |
V. no. |
WP no. |
Lead Bene-ficiary |
Nature |
Dissemination level |
Delivery date from Annex I (proj month) |
Actual / Forecast delivery date | Status / Not submitted |
Contractual Yes / No |
Comments |
|
D1.2 |
2nd periodic EuCARD report |
1 |
CERN |
R |
PU |
M38 |
|||||
|
D3.2.1 |
Performance analysis and physics potential of upgrades of existing neutrino facilities |
3 |
INFN |
R |
PU |
M40 |
|||||
|
D3.3.1 |
Proposal of the next global accelerator neutrino facility for Europe to build or help build. |
3 |
INFN |
R |
PU |
M40 |
|||||
|
D7.5.1 |
HTS 20 m 600 A link assembled |
7 |
CERN |
P |
PU |
M40 |
|||||
|
D7.2.1 |
Certification of the radiation resistance of coil insulation material |
7 |
PWR |
R |
PU |
M42 |
|||||
|
D8.3.1 |
One primary collimator with optional crystal feature, tested with beam |
8 |
CERN |
P |
PU |
M42 |
|||||
|
D9.4.1 |
ATF2 tests and CLIC IR study |
9 |
RHUL |
R |
PU |
M42 |
|||||
|
D10.6.1 |
Report on system test and performance |
10 |
DESY |
R |
PU |
M42 |
|||||
|
D9.5.1 |
RF phase monitor final report |
9 |
INFN |
R |
PU |
M45 |
|||||
|
D9.4.2 |
Laser Wire and Beam Position Monitor tests |
9 |
RHUL |
R |
PU |
M46 |
|||||
|
D2.1.1 |
Final report of WP2 DCO |
2 |
WUT, CERN |
R |
PU |
M48 |
|||||
|
D2.2.2 |
Final plan for the use and dissemination of foreground |
2 |
WUT, CERN |
R |
PU |
M48 |
|||||
|
D3.1.2 |
Final NEU2012 guidelines for an accelerator neutrino experiments programme |
3 |
INFN |
R |
PU |
M48 |
|||||
|
D4.1.2 |
AccNet Strategy for future proton & electron facilities in Europe |
4 |
CERN, CNRS |
R |
PU |
M48 |
|||||
|
D4.2.2 |
EuroLumi Strategy and issues for LHC IR, LHC injector and beam-parameter upgrade path(s), with comment on longer-term prospects, and for FAIR |
4 |
CERN |
R |
PU |
M48 |
|||||
|
D4.3.3 |
RFTECH strategy/result for cavity design, LLRF & HPRF systems and design integration, and costing tools |
4 |
CERN, TUL |
R |
PU |
M48 |
|||||
|
D7.1.1 |
HFM web-site linked to the technical & administrative databases |
7 |
CERN, CEA |
O |
PU |
M48 |
|||||
|
D7.3.1 |
Dipole model test results analyzed |
7 |
CEA |
R |
PU |
M48 |
|||||
|
D7.4.1 |
A HTS dipole insert coil constructed |
7 |
CNRS |
D |
PU |
M48 |
|||||
|
D7.6.1 |
Final prototype SC helical undulator measured |
7 |
STFC |
R |
PU |
M48 |
|||||
|
D8.1.1 |
ColMat web-site linked to the technical and administrative databases |
8 |
CERN, GSI |
O |
PU |
M48 |
|||||
|
D9.1.1 |
NCLinac web-site linked to the technical and administrative databases |
9 |
CERN, RHUL |
O |
PU |
M48 |
|||||
|
D9.2.1 |
Simulation and experimental results with report on the theoretical and scientific aspects of the CLIC module |
9 |
CERN |
R |
PU |
M48 |
|||||
|
D9.2.2 |
Prototypes with descriptive report (technical, design and fabrication) of the hardware prepared for the test module. |
9 |
CERN |
P |
PU |
M48 |
|||||
|
D9.3.1 |
CLIC Quadrupole Module final report |
9 |
CNRS |
R |
PU |
M48 |
|||||
|
D9.3.2 |
Final Focus Test Stand final report |
9 |
CNRS |
R |
PU |
M48 |
|||||
|
D9.5.2 |
Electro optical monitor final report |
9 |
INFN |
R |
PU |
M48 |
|||||
|
D10.1.1 |
SRF web-site linked to the technical and administrative databases |
10 |
DESY, CEA |
O |
PU |
M48 |
|||||
|
D10.5.1 |
HOM electronics and code to probe beam centring on 3.9 GHz cavities |
10 |
DESY |
R |
PU |
M48 |
|||||
|
D10.5.2 |
Report on HOM experimental methods and code |
10 |
DESY |
R |
PU |
M48 |
|||||
|
D11.1.1 |
ANAC web-site linked to the technical and administrative databases |
11 |
INFN |
O |
PU |
M48 |
|||||
|
D1.3 |
3rd periodic EuCARD report |
1 |
CERN |
R |
PU |
M50 (31/05/2013) |
|||||
|
D1.4 |
Final project report |
1 |
CERN |
R |
PU |
M50 |
|||||